• Select licence on map for further information 
    Private: North East England
    PEDL068PEDL259PEDL258PEDL343P1929P1241P2304

    PEDL068

    Licences Operator Egdon Interest Area km² Exploration Targets Work programme
    PEDL068 Egdon Resources U.K. Limited 68.00% 35.20 Shale and Conventional Exploration Evaluating future development options at Kirkleatham

    PEDL259

    Licences Operator Egdon Interest Area km² Exploration Targets Work programme
    PEDL259 Third Energy Onshore Limited 50.00% 139.00 Shale and Tight Gas Exploration Commitment in first five years; drill 1 well or drop licence

    PEDL258

    Licences Operator Egdon Interest Area km² Exploration Targets Work programme
    PEDL258 Egdon Resources U.K. Limited 100.00% 0.5 Conventional – Purely to secure surface location for Resolution Commitment in first five years; drill 1 well or drop licence

    PEDL343

    Licences Operator Egdon Interest Area km² Exploration Targets Work programme
    PEDL343 Third Energy Onshore Limited 17.50% 110.00 Shale and Tight Gas Exploration Cloughton Tight Gas Discovery. Commitment in first five years; new 3D, drill 1 well or drop licence

    KM-8 fracking results will be of interest in future.

    P1929

    Licences Operator Egdon Interest Area km² Exploration Targets Work programme
    P1929 Egdon Resources U.K. Limited 100.00% 201.5 Conventional Exploration Resolution Prospect - upgraded mean prospective gas resource estimated at 337bcf. Offshore well cost comparale with onshore to offshore well and has lower delivery risk (technical & planning). Minimum offshore facility development being considered - gas processing in both cases. Offshore 3D seismic acquisition planned to optimise appraisal drilling programme. Seeking farm-in/technology partner prior to seismic and drilling

    P1241

    Licences Operator Egdon Interest Area km² Exploration Targets Work programme
    P1241 Centrica Energy 10.00% 43.00 Producing Gas field Operator planning for extended field life. Backout repayment underway. Flow meter installed & Primary Production underway since 2018

    P2304

    P2304 Egdon Resources U.K. Limited 100.00% 166.00 Conventional Exploration Licence contains a mapped extension of the Resolution gas accumulation and an additional proven gas discovery. We will now work to integrate our evaluation of the new licence into our detailed understanding of P1929 with a view to progressing appraisal of the proven gas resources in the combined area.

Egdon Resources has been active in exploration and production in the Cleveland Basin in the North East since 2000 and has drilled several exploration wells and developed the Kirkleatham gas field on PEDL068.  Planned activity on our current licences includes drilling an exploration well on the Resolution prospect in P1929 from onshore to offshore or from an offshore location and further drilling at Kirkleatham. Under the Third Energy operated 14th Round awards activity will include potential appraisal of the Cloughton Tight Gas field and exploration of the new Tees licence surrounding Kirkleatham.

The planned fracking by Third Energy of its KM-8 tight gas discovery may open up an exciting new play in the region when it is finally approved with read through to Cloughton.

Offshore, our non-operated Ceres gas field continues to outperform expectations in late field life with Primary production having resumed in October 2018.

Onshore

Licences Operator Egdon Interest Area km² Exploration Targets Work programme
PEDL068 Egdon Resources U.K. Limited 68.00% 35.20 Shale and Conventional Exploration Evaluating future development options at Kirkleatham
PEDL259 Third Energy Onshore Limited 50.00% 139.00 Shale and Tight Gas Exploration Commitment in first five years; drill 1 well or drop licence
PEDL343 Third Energy Onshore Limited 17.50% 110.00 Shale and Tight Gas Exploration

Cloughton Tight Gas Discovery. Commitment in first five years; new 3D, drill 1 well or drop licence

KM-8 fracking results will be of interest in future

PEDL258 Egdon Resources U.K. Limited 100.00%  0.50 Conventional – Purely to secure surface location for Resolution  Commitment in first five years; drill 1 well or drop licence

Offshore

Licences Operator Egdon Interest Area km² Exploration Targets Work programme
P1241 Centrica Energy 10.00% 43.00 Producing Gas field Operator planning for extended field life Backout repayment underway flow meter installed. Primary production underway since 2018
P1929 Egdon Resources U.K. Limited 100.00% 201.5 Conventional Exploration Resolution prospect upgraded mean prospective gas resource estimated at 337bcf Offshore well cost comparable with onshore to offshore well and has lower delivery risk (technical and planning)Minimum offshore facility development being considered – gas processing in both cases offshore 3D seismic acquisition planned to optimise appraisal drilling programme Seeking farm-in/technology partner prior to seismic and drilling
P2304 Egdon Resources U.K. Limited 100.00% 166.00 Conventional Exploration Licence contains a mapped extension of the Resolution gas accumulation and an additional proven gas discovery. We will now work to integrate our evaluation of the new licence into our detailed understanding of P1929 with a view to progressing appraisal of the proven gas resources in the combined area.